Completed Projects 

FAFB - Sere water mains

As the Subcontractor we performed Excavation, including trench safety, rock breaking, import and export of materials, install of water mains from 12" pvc/ductile, to 6" pvc/ductile. 

Contract - $1,200,000

100 Working days


Washinton national guard - landscape boundary

As a prime contractor we self performed, excavation, concrete curbs and paving, final grading.

Contract - $225,000

40 Working days


fafb - miller park splash pad 

As the Subcontractor we performed Excavation, Utilities, Concrete structural/flat work, sewer pipe, water pipe hot tap, electrical trenching, and landscaping. The Prime contractor was Rore Const. 

Contract - $200,000

40 Working days


Walmart Spokane Wellesly - online pickup 

As the Subcontractor we performed Excavation, Utilities, Concrete structural and flat work. The Prime contractor was Sletten Const. 

Contract - $206,000

45 Working days


Walmart Spokane valley - online pickup 

As the Subcontractor we performed Excavation, Utilities, Concrete structural and flat work. The Prime contractor was Sletten Const. 

Contract - $354,000

65 Working days


Costco St. George UT - Chiller and freezer 

As the Prime Contractor we self-performed Excavation, Concrete structural and flat work. Sub-contracted scopes include, Fire sprinklers, Asphalt, Landscaping, Concrete cutters.

Contract - $655,000

65 Working days


Veterans Grant - hulse bathroom addition

As a prime contractor we designed this project, we also managed, and self performed, Excavation, concrete structural/Flat, Framing, siding, roofing with sub contractors for Plumbing, electrical, Paint, and epoxy flooring.

Contract - $136,000

45 Working days


STA - Eagal station 

As the Prime Contractor we self-performed Excavation, Concrete structural and flat work, signage, curved butcher block seats and sheet metal. other scopes included plumbing, framing, Roofing, painted logos, electrical. This particular project was a challenging due to the curved structure be.



Contract - $845,000

45 Working days


Spokane valley Costco - Chiller addition

We acted as a sub-contractor suppling Excavation and concrete labor.



Contract - $160,000

45 Working days


Bia - Spokane detention center lighting and hvac

Operating as an Indian owned small business, D-McP managed this contract using multiple skilled sub-contractors. We completed a lighting retrofit that was projected to Save upward of $9,000 per month! We also replaced the HVAC roof unit and curb. 



Contract - $101,000

45 Working days


Lakehurst Dr - Side road

100% SELF PERFORMED. Installed a side road at a private residence on diamond lake in medical lake WA. This included a 1000lb breaker, and block wall. This was by far the steepest hill side we have worked on. We learned a lot and were successful in completing the work!!



Contract - $30,000

  15 Working days


WSU Spokane - South Parking lot 

This was a locally funded public works project consisted Impanation of complete TCS select demolition to remove Curbs, Side Walks, Trees and other obstructions. Clear, Grub and prep for new driveway entry with COS approach with multiple ped ramps. Included 2 60x12 swales with Ductile equalizer pipes. DMCP self-performed the excavation, and hauling. We were able to complete the main scope of work withing 7 days, on the seventh day we had excavation, rolled curb and back top completed.



Contract - $163,000

  21 Working days


Cheney Safe Routs to school 

This was a locally funded public works project consisted Impanation of complete TCS select demolition to remove Curbs, Side Walks, Trees and other obstructions. Clear, Grub and prep for new monolithic sidewalk (1,500 LFT) and 900 linear feet of 10 foot asphalt paths. DMCPC also designed and installed pit-run bridging for the path at the park in order to keep it up out of a saturation prone area.



Contract - $475,000

  40 Working days


STa Lighted Pit Repair  

This was a locally funded public works project consisted of select demolition to remove corroded steel framing at three lighted maintenance pits, installation of new framing, new fall protection, cleaning and application of new protective coatings, as well as the repair or addition of structural support in select areas. 


Client Representative: Jessica Charlton 

Spokane Transit Authority 



Contract - $291,000

  66 Working days


Deck And Roof 

Remove and replace old out of spec deck.  

Client Representative: Residential


$26,000

20  working days


Helical piles Washintion St.  

Excavate and install Helical Piles repair all damages  

Client Representative: Residential


$32,000

5 working days

1 Subcontractors

1 Structural Engineer 

Orchard Park Pavilion  

Construct 4k square foot Canopy  

Client Representative: Scott Bernhard City of Liberty Lake


$563,000

50 working days

8 Subcontractors


Fairchild Air Force Base 

Commercial Kitchen Appliance Install  

Client Representative: Tad Miles


$12,000

3 working days

3 Subcontractors

ONION CREEK SCHOOL DISTRICT 30 

Roof Over Slab 

School Representative: Hugh Humes

Onion Creek School District 


Value $151,776

28 working days

3 Subcontractors

Concrete  Paths

Concrete Paths

Representative: Residential


Value $10,000

5 working days

0 Subcontractors

STCu bonner 

General Carpentry

Representative: Meridian Construction 


Value $5,000

5 working days

0 Subcontractors